Quick Answer

Resource leveling is a scheduling technique in which the planners assign resources to the most critical tasks first, then float other tasks to share the remaining resources in turn so that overall project completion remains on schedule. This technique allows efficient allocation of resources but may delay the project.

Continue Reading

Full Answer

Another project scheduling technique is the critical path method, where the planners determine the minimum amount of time they need to complete the project. They do this by estimating the duration of each project task and the earliest possible start and finish dates for each task. This information helps determine the most efficient order in which the team can perform each task and provides a realistic completion date for the project.