Formwork is the term given to either temporary or permanent moulds into which concrete or similar materials are poured. In the context of concrete construction, the falsework supports the shuttering moulds.
Formwork comes in three main types:
Some of the earliest examples of concrete slabs were built by Roman engineers. Because concrete is quite strong in resisting compressive loads, but has relatively poor Tensile or torsional strength, these early structures consisted of arches, vaults and domes. The most notable concrete structure from this period is the Pantheon in Rome. To mold these structure, temporary scaffolding and formwork or falsework was built in the future shape of the structure. These building techniques were not isolated to pouring concrete, but were and are widely used in Masonry. Because of the complexity and the limited production capacity of the building material, concrete’s rise as a favored building material did not occur until the invention of Portland cement and reinforced concrete.
With preassembled timber modules or steel or aluminium modules. to be completed
These systems consist of slab formwork “tables” that are reused on multiple stories of a building without being dismantled. The assembled sections are either lifted per elevator or “flown” by crane from one story to the next. Once in position the gabs between the tables or table and wall are filled with “fillers”. They vary in shape and size as well as their building material. The use of these systems can greatly reduce the time and manual labor involved in setting and striking the formwork. Their advantages are best utilized by large area and simple structures. It is also common for architects and engineers to design building around one of these systems.
A table is built much the same way as a beam formwork but the single parts of this system are connected together in such a way making them transportable. The most common sheathing is plywood, but steel and fiberglass are also in use. The joist are either made from timber, wood I-beams, aluminium or steel. The Stringers are sometimes made of wood I-beams but usually from steel channels. These are fastened together (screws, weld or bolted) to become a “deck”. These decks are usually rectangular but can also be other shapes.
Crane handled
This approach consists of assembling or producing the tables with a large formwork area that can only be moved up a level by crane. Typical widths can be 15, 18 or 20ft. or 5 to 7 meters but their width can be limited, so that it is possible to transport them assembled, without having to pay for an oversize load. The length vary and can be up to 100ft. (or more) depending on the crane capacity. After the concrete is cured, the decks are lowered and moved with rollers or trolleys to the edge of the building. From then on the protruding side of the table is lifted by crane whiles the rest of the table is rolled out of the building. After the center of gravity is outside of the building the table reattached to another crane and flown to the next level or position. This technique is fairly common in the United States and east Asian countries. The advantages of this approach are the further reduction of manual labor time and cost per sqft. or m² of slab and a simple and systematic building technique. The disadvantages of this approach are the necessary high lifting capacity of building site cranes, additional expensive crane time, higher material costs and little flexibility.
crane fork or elevator handled
By this approach the tables are limited in size and weight. Typical widths are between 6 to 10ft. or 2 to 3 meters, typical lengths are between 12 and 20ft. or 4 to 7 meters, though table sizes may vary in size and form. The major distinction of this approach is that the tables are lifted either with a crane transport fork or by material platform elevators attached to the side of the building. They are usually transported horizontally to the elevator or crane lifting platform single handedly with shifting trolleys depending on their size and construction. Final positioning adjustments can be made by trolley. This technique enjoys popularity in the US, Europe and generally in high labor cost countries. The advantages of this approach in comparison to beam formwork or modular formwork is a further reduction of labor time and cost. Smaller tables are generally easier to customize around geometrically complicated buildings (round or non rectangular) or to form around columns in comparison to their large counterparts. The disadvantages of this approach are the higher material costs and increased crane time (if lifted with crane fork).
For removable forms, once the concrete has been poured into formwork and has set (or cured), the formwork is struck or stripped (removed) to expose the finished concrete. The time between pouring and formwork stripping depends on the job specifications, the cure required, and whether the form is supporting any weight, but is usually at least 24 hours after the pour is completed. For example, the California Department of Transportation requires the forms to be in place for 1-7 days after pouring, while the Washington State Department of Transportation requires the forms to stay in place for 3 days with a damp blanket on the outside.
Spectacular accidents have occurred when the forms were either removed too soon or had been under-designed to carry the load imposed by the weight of the uncured concrete. Less critical and much more common (though no less embarrassing and often costly) are those cases in which underdesigned formwork bends or breaks during the filling process (especially if filled with a high-pressure concrete pump). This then results in fresh concrete escaping out of the formwork in a form blowout, often in large quantities.
Concrete exerts less pressure against the forms as it hardens, so forms are usually designed to withstand a number of feet per hour of pour rate to give the concrete at the bottom time to firm up. For example, wall or column forms are commonly designed for a pour rate between 4-8 ft/hr. The hardening is an asymptotic process, meaning that most of the final strength will be achieved after a relatively short time, though some further hardening can occur depending on the cement type and admixtures.
Wet concrete also applies hydrostatic pressure to formwork. The pressure at the bottom of the form is therefore greater than at the top. In the illustration of the column formwork to the right, the 'column clamps' are closer together at the bottom. Note that the column is braced with steel adjustable 'formwork props' and uses 20 mm 'through bolts' to further support the long side of the column.
Terminology