From numerous studies by Standish Group and others ref as of 1998 for traditional project management methods, only 44% of projects typically finish on time, projects usually complete at 222% of the duration originally planned, 189% of the original budgeted cost, 70% of projects fall short of their planned scope (technical content delivered), and 30% are cancelled before completion.
These traditional statistics are mostly avoided through CCPM. Typically, CCPM case studies report 95% on-time and on-budget completion when CCPM is applied correctly. Mabin and Balderstone, performed a meta-analysis of seventy-eight published case studies taken from the manufacturing and operational literature. They found that implementing Critical Chain resulted in mean reduction in lead-times of 69%, mean reduction of cycle-times of 66%, mean improvement in due date performance of 60%, mean reduction in inventory levels of 50% and mean increases in revenue / throughput of 68%. While these statistics may not entirely apply to the project management venue, they could be an indication to the magnitude of improvements possible when applying the same techniques to the project world.
In project management, the critical chain is the sequence of both precedence- and resource-dependent terminal elements that prevents a project from being completed in a shorter time, given finite resources. If resources are always available in unlimited quantities, then a project's critical chain is identical to its critical path.
Critical chain is used as an alternative to critical path analysis. The main features that distinguish the critical chain from the critical path are:
CCPM aggregates the large amounts of safety time added to many subprojects in project buffers to protect due-date performance, and to avoid wasting this safety time through bad multitasking, student syndrome, Parkinson's Law and poorly synchronised integration.
Critical chain project management uses buffer management instead of earned value management to assess the performance of a project. Some project managers feel that the earned value management technique is misleading, because it does not distinguish progress on the project constraint (i.e. on the critical chain) from progress on non-constraints (i.e. on other paths). Event chain methodology can be used to determine a size of project, feeding, and resource buffers.
Resources are then assigned to each task, and the plan is resource leveled using the 50% estimates. The longest sequence of resource-leveled tasks that lead from beginning to end of the project is then identified as the critical chain. The justification for using the 50% estimates is that half of the tasks will finish early and half will finish late, so that the variance over the course of the project should be zero.
Recognizing that tasks are more likely to take more rather than less time due to Parkinson's law, Student syndrome, or other reasons, "buffers" are used to establish dates for deliverables and for monitoring project schedule and financial performance. The "extra" duration of each task on the critical chain—the difference between the "safe" durations and the 50% durations—is gathered together in a buffer at the end of the project. In the same way, buffers are gathered at the end of each sequence of tasks that feed into the critical chain.
Finally, a baseline is established, which enables financial monitoring of the project.
When the plan is complete and the project ready to kick off, the project network is fixed and the buffers size is "locked" (i.e. their planned duration may not be altered during the project), because they are used to monitor project schedule and financial performance.
With no slack in the duration of individual tasks, the resources on the critical chain are exploited by ensuring that they work on the critical chain task and nothing else; bad multitasking is eliminated. An analogy is drawn in the literature with a relay race. The critical chain is the race, and the resources on the critical chain are the runners. When they are running their "leg" of the project, they should be focused on completing the assigned task as quickly as possible, with no distractions or multitasking. In some case studies, actual batons are reportedly hung by the desks of people when they are working on critical chain tasks so that others know not to interrupt. The goal, here, is to overcome the tendency to delay work or to do extra work when there seems to be time.
Because task durations have been planned at the 50% probability duration, there is pressure on the resources to complete critical chain tasks as quickly as possible, overcoming student's syndrome and Parkinson's Law.
Monitoring is, in some ways, the greatest advantage of the Critical Chain method. Because individual tasks will vary in duration from the 50% estimate, there is no point in trying to force every task to complete "on time;" estimates can never be perfect. Instead, we monitor the buffers that were created during the planning stage. A fever chart or similar graph can be easily created and posted to show the consumption of buffer as a function of project completion. If the rate of buffer consumption is low, the project is on target. If the rate of consumption is such that there is likely to be little or no buffer at the end of the project, then corrective actions or recovery plans must be developed to recover the loss. When the buffer consumption rate exceeds some critical value (roughly: the rate where all of the buffer may be expected to be consumed before the end of the project, resulting in late completion), then those alternative plans need to be implemented.