Staythorpe Power Station is a 1650MWe gas-fired power station between
Southwell and
Newark-on-Trent in
Nottinghamshire, next to the
River Trent and
Nottingham to Lincoln Line. It will be open in 2010.
History
The £600m plant near
Averham is currently under construction and is owned by the German company,
RWE. It is being built on the site of two former
CEGB coal-fired power station, the 360MW
Staythorpe A (built July 1950) and B (built May 1962). Staythorpe A was closed in 1989 and Staythorpe B in 1996. There is still a large
substation next to the
site of the former power stations, and a
monument Planning permission was given for the gas-fired power station as early as 1993, and construction originally began in 1998 by the previous owner
National Power, temporarily ceasing in 2000 due to over-supply of electricity, and a low price of electricity. Construction began again in early 2008, after RWE
decided to go ahead with Staythorpe in May 2007 at the expense of an alternative site at
Pembroke Dock. The Pembroke site will also now be built. Alstom has the
EPC contract.
Specification
It is a
CCGT-type power station that runs on natural gas. It will generate enough electricity for two million homes. It will consist of four modules, generating around 400MWe each, each with an
Alstom 288MWe
GT26B gas turbine,
heat recovery steam generator and
steam turbine. Electricity will be generated using Alstom
TOPGAS hydrogen-cooled
generators.